(L. Nageswara Rao, Hemant Gupta and Ajay Rastogi, JJ.)
Special Leave Petition (Civil) Diary No(s). 5960/2020
Malayan Banking Berhad _______________________ Petitioner;
v.
Ushdev International Ltd. and Others ____________ Respondent(s).
(With appln for condonation of delay in filing SLP)
Special Leave Petition (Civil) Diary No(s). 5960/2020; RPL No. 38/2019; and NOM No. 19/2016, decided on October 15, 2020
The Order of the court was delivered by
Order
1. Learned counsel for the petitioner states that High Court has committed an error in its interpretation of Section 14(1)A of Insolvency and Bankruptcy Code, 2016. He submits that the provision of moratorium is only applicable to civil suits filed against the corporate debtor. In this case, the suit has been filed by the corporate debtor and Section 14(1)A is not applicable.
2. Delay condoned.
3. Issue notice.
———